Wastewater Treatment Plant for Palm Jumeirah - Dubai, UAE

I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Introduction

Under the visionary leadership of Sheikh Mohamed Bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, Palm Jumeirah township was inaugurated as an iconic project constructed off the coast of the Emirate of Dubai. The project was built in the shape of a palm and has extended the stretch of Dubai coastline by more than 120 km. As Palm Jumeirah is the only modern structure seen from space, so is MetiPro’s on-site sewage treatment plant achieving many firsts.

Being host to some of the world’s renowned dignitaries and celebrities meant that all associated utilities demanded challenging innovations, adherence and commitment to maintaining the highest standards of environmental protection and architectural aesthetics. The location of the plant on prime land left an extremely limited space for plant buildings and respective facilities. Architecturally, the treatment plant is inside a circular building constructed below ground to keep it invisible. The given geometry, limited space and underground conditions presented a very difficult task of arranging the equipment, facilities and utilities. MetiPro employed the MBR (Membrane Bio-Reactor) process technology, which is the latest technology in treating waste. This process requires a considerably reduced footprint than other conventional schemes and has the added advantage of producing high-quality treated water.

Special designs were adopted for access to allow operational access and equipment maintenance. Limited headroom dictated the use of a specially designed serpentine monorail that covers the whole workspace. The status of the location demanded zero tolerance for any unpleasant odor emissions.

The ventilation system, dehumidifier and odor control units in the workspace were carefully designed, taking into consideration these stringent demands.

Scope of Work

This included the detailed engineering, manufacture, inspection, supply, storage, installation, testing and commissioning, start-up, performance test and training of personnel at site. It also included operation and maintenance of the plant for eight years.

Plant General Information

The sewage treatment facility mainly comprises the following units:

  • Inlet works

  • Biological Treatment

  • Sludge Handling

  • Chemical cleaning

  • Electrical and Control system

Plant Technical Characteristics

Raw sewage from the residential community is transferred to a main sewage lift station through two intermediate pumping stations.

The sewage treatment plant is designed to treat 18,000 m³/day of domestic sewage. The collected raw sewage is received through a 600 mm diameter underground main and the incoming flow is metered before it enters the treatment units.

Plant Data Summary

  • Average daily flow: 18,000 m³/d

  • Peak daily design flow: 21,700 m³/d

  • Peak factor: 2.5

  • Peak hourly flow: 1,875 m³/h

  • Peak flow duration: 2 hours

Influent Analysis

Parameter Value Unit
Temperature 22 – 35 °C
BOD₅ 250 mg/l
COD 500 mg/l
TKN 55 mg/l
Assumed biodegradable TKN 50 mg/l
Suspended solids 250 mg/l
Phosphates 8 mg/l
Alkalinity Min. 210 mg/l
Oil & Grease < 40 mg/l
pH 6 – 9
Ammonia Nitrogen 35 mg/l
Ambient Temperature 10 minimum / 50 maximum °C

Treated Water Quality

Parameter Value Unit
BOD < 10 mg/l
COD < 50 mg/l
TKN < 5 mg/l
Suspended solids < 10 mg/l
Ammonia-Nitrogen NH₃(N) < 3 mg/l
Total Nitrogen (TN) < 30 mg/l
Fecal Coliform < 10 mg/l

Process Description

Inlet Works

Metered raw sewage from the mains is released into a concrete channel through two 3 mm perforated plate fine screens operating on a duty/standby basis. While screenings are removed, the screen surface is cleaned by spray nozzles as the basket rotates. For clean and easy handling, the collected waste from the screens is compacted and dewatered up to 40% w/w. A vortex type grit removal system with grit classifier is installed after the screens to remove heavy grit particles.

Partially treated raw sewage enters a two compartment equalization tank. The tank is constantly purged with enough air to maintain the sewage in agitation and prevent it turning septic.

Downstream membrane treatment is divided into six process trains to cater for plant turndown and to provide flexibility in operation. The common pump sump has six duty/standby feed pumps dedicated to transfer sewage to the anoxic tanks.

The biological treatment of each process train comprises the following process units:

Anoxic Tank

The anoxic tank receives partially pre-treated equalized sewage that has been intimately mixed with recycled flow from the anoxic recycle pumps. The returned flows contain nitrate due to the nitrification of ammonia in the membrane tank. Bacteria utilize the soluble and particulate COD in the incoming sewage to effect de-nitrification under anoxic conditions. Submerged mixers in each anoxic tank keep the bacteria in suspension and homogeneously mixed with the soluble nitrate.

Aeration Tanks

Sewage from the anoxic tanks passes to the aeration tanks by gravity. The aeration tanks provide an aerobic environment to ensure nitrification of ammonia and oxidation of BOD, achieved by the provision of high efficiency fine bubble diffused aeration. The air supply to the diffuser system is monitored and controlled automatically to maintain optimum residual dissolved oxygen (DO) concentration in the tanks.

Membrane Bioreactor Tanks

Six membrane bioreactor tanks serve the function of secondary aeration tanks, whilst also assisting in the provision of air for the biological degradation processes. Each membrane tank contains 12 membrane units arranged in a double-deck configuration. To prevent surface fouling, membranes are continuously scoured by air supplied through diffused air pipe distributors below the membrane block.

Provision was made to chemically clean the membranes, if and when required. A diffuser flushing system is used to periodically flush the coarse bubble diffusers. Flux rate control is a critical operational feature, hence flow through the membranes is controlled by modulating the permeate control valve to achieve the required flow rate through the flow meter on the permeate line.

Recycle Pump Control

The recycle pumps are subjected to intermittent operation to ensure a maximum recycle rate in low flow conditions. Intermittent operation is set according to the pre-determined schedule controlled by a PLC.

Disinfection

The membrane process removes a large portion of bacteria from the sewage. Chlorination using sodium hypochlorite is imparted into treated streams to remove or inactivate any pathogenic bacteria that may grow in the tanks.

Sludge Digestion and Handling

Biological sludge is pumped to sludge digesters where it is digested and stabilized under aerobic conditions. Digested sludge is pumped to a dewatering centrifuge to produce sludge of 20–25% dryness. Concentrate from the centrifuge is returned to the plant inlet for recovery.

Electrical and Control Equipment

This includes state-of-the-art SCADA system, PLC control panels and MCCs. SCADA is implemented with graphical depiction of process, as well as graphical representation of process parameters and plant data that is also archived and retrievable. Power to the STP plant is fed from the facility substation which is equipped with dual incomers mains supply from DEWA as well as emergency supply from a generator. The design of the control equipment has taken into consideration the necessity for separate and independent operation of the MBR streams, so that failures in the control equipment associated with one stream will result in the shut down of the affected stream only.

Project execution involved complying with the international standards and specifications drawn by the consultants. Important factors such as availability of plant, efficient use of manpower, high reliability and simplicity of maintenance have been considered in the design. The plant utilized minimum space whilst maintaining the overall architectural requirements. Technically, it provided a modern up-to-date process that ensures consistent water treatment quality. MetiPro completed this most challenging task to the entire satisfaction of the owner, and the successful operation of this entire complex was subsequently managed by MetiPro’s workforce.

Key Data

Location Dubai, UAE