Introduction
In line with the progressive UAE Centennial 2071 vision and the United Nations 2030 Agenda for Sustainable Development, “The sustainable environment and infrastructure” goal has been marked as a key priority for the UAE and the Emirate of Sharjah.
The AED 210 million Sharjah Sewage Treatment Plant upgrade project for Phase 4 and 5, awarded to MetiPro, is one of the many iconic projects the Sharjah Directorate of Public Works (DPW) has developed. The objective of the project is to increase the capacity of the existing plants from 27,400 m³/day to 65,000 m³/day per phase, reaching a total capacity of 130,000 m³/day. This is to accommodate the increased inflow and the growing demand for urban spaces in the second largest Emirate in terms of population.
MetiPro placed a strong emphasis on creating a transparent decision-making process, so each stage of the project was reviewed collaboratively with the client and agreed upon prior to the design stage. This helped to develop a highly energy-efficient treatment method and optimum performance measures to meet project delivery and system design characteristics.
Through implementing a non-traditional case study approach for the retrofitting project, MetiPro avoided potential interruptions to the ongoing operations of the plant.
MetiPro’s scope of work included the design, supply, retrofit, assessment, and repair of existing structures, as well as the construction of new structures. MetiPro was also responsible for the installation of equipment, the refurbishment of some existing facilities, testing and commissioning.
As part of the project, various existing facilities, including aeration tanks, raw sewage inlet area, gravity sand filter building and the sludge facilities building, were all upgraded. Additional new facilities, such as blower buildings, one new filter building, and new clarifiers (lamella tube clarifiers), were then built to double the capacity of the STP with minimum construction and maximum production.
The project achieved over 1.9 million man-hours without a single injury or time lost during the construction of the plant. This is an outcome of regular health, safety, and environment (HSE) trainings to ensure maximum safety at the construction site. All project works had risk analysis and proper documentation managed by relevant departments to avoid risk and reworks.