Introduction
Sousa is a tourist city located on the south Mediterranean coast. It is home to several beach resorts that are flocked by thousands of tourists every year. The city constitutes one of the major income inducing areas for the Tunisian government, and so the Tunisian government decided to establish a new water treatment plant. The new plant has a capacity of 26,000 m³/day for potable use, and can accommodate the increasing demand for water in this busy area.
The client, SONDE (Société Nationale d’Exploitation et de Distribution des Eaux), tendered the project on an urgent basis in a bid to meet the anticipated increase in demand which was expected in the summer of 2004. MetiPro was entrusted by SONDE to execute and deliver the plant within 4 months from date of award. The project encompassed the complete design, manufacturing, installation and commissioning of the plant, followed by two months performance reliability test. Classroom and field training of client personnel were also part of the services rendered under this contract.